First train launched on reconstructed section of Sumgayit-Yalama railway

2021-12-27

The movement of trains launched on the reconstructed section of Sumgayit-Yalama railway, which is an important part of the North-South international transport corridor.
Reconstruction works on the two-lane Sumgayit-Yalama railway, are being carried out along with transportation. Along with the existing line in the direction of Shabran-Charhi, a new line was also put into operation on Sumgayit-Yalama railway. Within the project, 23 kilometres of the railway were reconstructed and put into operation.
So far, a new rail-sleeper network has been installed on the 65-kilometer section of the road. In general, 22.12% of reconstruction works have been completed. Currently, in accordance with the technological sequence, construction and installation work is underway.
Sumgayit-Yalama railway reconstruction project is being implemented on the basis of joint financing within the framework of the Railway Sector Development Program in accordance with loan agreements between the Government of Azerbaijan and the Asian Development Bank dated December 19, 2017 and between the Government of Azerbaijan and the French Development Agency dated March 11, 2019.
Reconstruction work began on February 18, 2020.

ILHAM ALIYEV

ILHAM ALIYEV

President of the Republic of Azerbaijan

HEYDAR ALIYEV

HEYDAR ALIYEV

The national leader of Azerbaijani people

MEHRIBAN ALIYEVA

MEHRIBAN ALIYEVA

First Lady of Azerbaijan

Azerbaijan Railways

Azerbaijan Railways

Closed Joint Stock Company

ADY CONTAINER

ADY CONTAINER

Limited liability company

AzRusTrans

AzRusTrans

Limited liability company


ADY Express
  • Azərbaycan
  • Русский
  • English
ADY Express
All rights reserved. © 2016